Main Span(s): Prestressed concrete [5] Box beam or girders - Multiple [05]
Approach Span(s): Other [00]
Deck: Concrete Precast Panels [2] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 8 m = 26.2 ft
Main Spans: 1 at 8 m = 26.2 ft
Approach Spans: 0
Skew: 80
Width, Roadway: 9.1 m = 29.9 ft (2 Lanes) and Out-To-Out: 15.2 m = 49.9 ft for a 9.1 m = 29.9 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Cadillac [12320]: Wexford County [165], Michigan [26]
Owned by City or Municipal Highway Agency [04], DOT District: 2
IN CADILLAC
Condition
Deck: Very Good [8]
Superstructure: Good [7]
Substructure: Very Good [8]
Loading
Design: MS 18+Mod / HS 20+Mod [6]
Operating: 51.8 metric ton = 57.0 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 40.2 metric ton = 44.2 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Better than present minimum criteria [7]
Deck Geometry: Meets minimum tolerable limits to be left in place as is [4]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Basically intolerable requiring high priority of replacement [2] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: April 1999 [499] and Frequency: 24
Future Work
Work Needed: Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Bridge Detour: 0.3 km = 0.2 mi
Traffic
ADT: 4700 (2004) and Trucks: 10%