Main Span(s): Prestressed concrete continuous [6] Stringer/Multi-beam or girder [02]
Approach Span(s): Other [00]
Deck: Concrete Cast-in-Place [1] with Wearing Surface: Monolithic Concrete (concurrently placed with structural deck) [1]
Bridge Dimensions
Length: 91.4 m = 299.9 ft
Main Spans: 2 at 45.1 m = 148.0 ft
Approach Spans: 0
Skew: 0
Width, Roadway: 12.8 m = 42.0 ft (2 Lanes) and Out-To-Out: 13.4 m = 44.0 ft for a 12.8 m = 42.0 ft approaching roadway.
Vertical Clearance: 99.99 m = 328.1 ft and Navigational Clearance: 0 = N/A
Location
Unknown [00000]: Chelan County [007], Washington [53]
Owned by State Highway Agency [01], DOT District: 2
5.5 E JCT SR 207
Condition
Deck: Very Good [8]
Superstructure: Very Good [8]
Substructure: Very Good [8]
Loading
Design: HL93 [A]
Operating: 51.5 metric ton = 56.7 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Inventory: 39.9 metric ton = 43.9 tons (Load and Resistance Factor Rating (LRFR) rating reported by rating factor (RF) method using HL-93 loadings [8])
Appraisal
Structural: Equal to present desirable criteria [8]
Deck Geometry: Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Road Alignment: Equal to present desirable criteria [8]
Waterway: Equal to present desirable criteria [8] and Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Inspections
Date: August 1999 [899] and Frequency: 24
Future Work
Work Needed: Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Bridge Detour: 15.9 km = 9.9 mi
Traffic
ADT: 5583 (2019) and Trucks: 10%
Future ADT: 7012 (In 2039
)